Cookie Consent by Free Privacy Policy website Adjustments to Domestic Production due to Earthquake in February 2021 (as of February 16)
febbraio 16, 2021 - Toyota

Adjustments to Domestic Production due to Earthquake in February 2021 (as of February 16)

Comunicato Stampa disponibile solo in lingua originale. 

Toyota would like to extend its sincere sympathy to those affected by the earthquakes that occurred on February 13 (Sat), and hope for the earliest possible recovery of the affected areas.

Due to the effects of the earthquake, adjustments will be made to production operations of plants for completed vehicles in Japan as follows.

We sincerely apologize for the inconvenience caused to our suppliers and people in those regions, due to these changes.

Production suspension for 14 production lines at nine plants (Among a total of 28 lines at 15 plants)

Plant

Period of production suspension 

(February)

Production Vehicle

Toyota Motor Corporation

Takaoka Plant

Production line #2

18 (Thu), 19 (Fri), 20 (Sat)

Harrier, Prius α, RAV4

Toyota Motor Corporation

Tahara Plant

Production line #1

Prado, GX, 4Runner

Production line #3

17 (Wed), 18 (Thu), 19 (Fri), 20 (Sat)

LS, IS, RC, NX

Toyota Motor Kyushu Co., Ltd.

Miyata Plant

Production line #1

19 (Fri) 2nd shift, 20 (Sat)

NX, UX, CT

Production line #2

20 (Sat)

ES, RX

Toyota Motor East Japan, Inc. (TMEJ)

Iwate Plant

Production line #1

18 (Thu) 2nd shift, 19 (Fri), 20 (Sat)

C-HR, Aqua

Toyota #auto Body Co., Ltd.

Fujimatsu Plant

Production line #1

17 (Wed) 2nd shift, 18 (Thu), 19 (Fri), 20 (Sat)

LC70

Toyota #auto Body Co., Ltd.

Yoshiwara Plant

Production line #1

LC200/LX

Production line #2

LC70

Gifu #auto Body Co., Ltd.

Production line #2

18 (Thu), 19 (Fri), 20 (Sat)

Coaster

Toyota Industries Corporation

Production line #301

17 (Wed), 18 (Thu), 19 (Fri), 20 (Sat)

RAV4

Production line #302

Hino Motors, Ltd.

Hamura Plant

Production line #1

18 (Thu), 19 (Fri), 20 (Sat)

Land Cruiser Prado, FJ Cruiser

Production line #2

Dyna

Notes

  • Line #2 at Gifu #auto Body operates at one shift.
  • 1st shift only for February 20 (Sat).

 

Ti potrebbe interessare anche

aprile 11, 2024
aprile 05, 2024
aprile 05, 2024

La GR Yaris Rally Cup è pronta ad accendere i motori e l’entusiasmo degli appassionati presentando, al primo appuntamento della pr...

Hilux MY24 è pronto a rinnovarsi: icona di qualità, affidabilità e durabilità Toyota, rimane un punto di riferimento per i clienti...

Toyota Motor Italia e KINTO, in qualità di Mobility Service Provider della AS Roma,  annunciano il loro impegno nel progetto “Tien...